There's been some delays on the manufacturing/tooling side, but I believe everything will be done by the end of the week. I'll call in tomorrow to make sure, and if so, here is the tentative "new" release schedule:

Thursday, March 8: Plates Arrive.
Saturday, March 10: First half of nubs are completed and qc'd
Sunday, March 11: Second half of nubs are completed and qc'd
Sunday Night, March 11: 1.1A Arms are cut=>>Go/No Go
Monday, March 12: Tentative ship date
Monday, March 19: "Rain Check"